Step 3a: Build pib´s neck (Adv)
Tutorial: pib#5 NeckPib's Neck consists of 11 3D-printed parts and can be assembled in the following 12 steps Make sure to calibrate the Motors first before assembling the neck! |
|
|---|
Overview: Needed Parts
3D Printable Parts:
| Non-printable Parts:
|
|---|
Overview: 3D Printable Parts
A71s-Inner_part_S
| A72s-Top_part_S |
A73-Cover_neck
| A75s-L-Neck_Left_S |
A75s-R-Neck_Right_S | A76-Neck_Middle |
A81-Motor_shaft | A82-Neck_axis |
A83-Motor_Adapter_Neck
| A77s-Neck_motor_wedge_S |
A78s-Nodding_motor_wedge_S
|
|
Step-by-Step Tutorial
Step 0: Calibrate motors | Difficulty: 2/5 |
Make sure all motors in this tutorial are calibrated according to tutorial "step 1c motor calibration" |
|
Step 1: Pressfit the nuts | Difficulty: 1/5 |
Insert 6x S01-M3_nut into the designated slots of A75s-L-Neck_Left_S and A75s-R-Neck_Right_S. Needed Parts: 6x S01-M3_nut, 1x A75s-L-Neck_Left_S, 1x A75s-R-Neck_Right_S |
|
Step 2: Place the Motor in the neck | Difficulty: 2/5 |
Connect the servo cable to E27-STS3215 according to the wiring diagram. Make sure to place a S01-M3_nut inside of A77s-Neck_motor_wedge_S. Position the motor and secure it with A77s-Neck_motor_wedge_S and 2x S03-M3x25 screws. Needed Parts: 1x A77s-Neck_motor_wedge_S, 2x S03-M3x25, 1x S01-M3_nut |
|
Step 3: Connect A76 and A75 | Difficulty: 1/5 |
Attach A76-Neck_Middle to A75s-L-Neck_Left_S and A75s-R-Neck_Right_S using 4x S03-M3x20 screws. Needed Parts: 1x A76-Neck_Middle, 4x S03-M3x20 |
|
Step 4: Motor Adapter Installation | Difficulty: 2/5 |
Attach STS3215-Metal-motor-Adapter-L to A71s-Inner_part_S using 4x S03-M3x8 screws. Needed Parts: 1x STS3215-Metal-motor-Adapter-L, 1x A71s-Inner_part_S, 4x S03-M3x8 |
|
Press 3x S01-M3_nut into the designated slots of A71s-Inner_part_S. Needed Parts: 3x S01-M3_nut |
|
Step 5: place Ballbearing | Difficulty: 2/5 |
Place 1x M04-Ballbearing_60x78x10, in the shown spot of A76. Needed Parts: 1x M04-Ballbearing_60x78x10, |
|
Step 6: Inner Part Installation | Difficulty: 2/5 |
Insert A71s-Inner_part_S into the M04-Ballbearing_60x78x10 and secure it with 1x S03-M3x40 screw. Needed Parts: 1x M04-Ballbearing_60x78x10, 1x S03-M3x40 |
|
Step 7: Insert Nuts | Difficulty: 2/5 |
Insert 2x S01-M3_nut into the designated slots of A72s-Top_part_S. Needed Parts: 2x S01-M3_nut |
|
Step 8: Top Part Installation | Difficulty: 1/5 |
Attach A72s-Top_part_S using 2x S03-M3x30 screws and 1x S03-M3x18 screw. Needed Parts: 2x S03-M3x30, 1x S03-M3x18 |
|
Step 9: Motor Installation | Difficulty: 2/5 |
Attach A83-Motor_Adapter_Neck and STS3215-Metal-motor-Adapter-L to E27-STS3215 using 4x S03-M3x10 screws. Needed Parts: 1x A83-Motor_Adapter_Neck, 1x STS3215-Metal-motor-Adapter-L, 4x S03-M3x10 |
|
Make sure to connect the Servo cable according to the wiring diagram. Place the assembled unit into the designated position in A72s-Top_part_S. |
|
Insert 1x S01-M3_nut into the designated slot of A78s-Nodding_motor_wedge_S and secure it using 2x S03-M3x25 screws. Needed Parts: 1x A78s-Nodding_motor_wedge_S, 1x S01-M3_nut, 2x S03-M3x25 |
|
Step 10: Ball Bearing and Motor Shaft Installation | Difficulty: 2/5 |
Insert 2x M21-15x21x4-Ballbearing into the designated slots. Secure A81-Motor_shaft using 1x S03-M3x40 screw. Needed Parts: 2x M21-15x21x4-Ballbearing, 1x A81-Motor_shaft, 1x S03-M3x40 |
|
Step 12: Neck and Head Connection |
|
Connect the neck to the head by inserting A82-Neck_axis into the designated position. Secure it with 1x S03-M3x16 screw. Then attach A02-Face_neck_clamp using 2x S03-M3x30 screws. Needed Parts: 1x A82-Neck_axis, 1x A02-Face_neck_clamp, 1x S03-M3x16, 2x S03-M3x30 |
|
Congratulations! The Neck is AssembledE-Mail Support: team@pib.rocks | Discord: discord.gg/GRdpyeDu7P | Web: pib.rocks | Shop: shop.pib.rocks |